Short answer: add up the stages. Design and drawing approval take as long as the answers do. Production at our factory takes 35–45 days after drawing approval and deposit. Then come checks, crating, trucking, sea freight, customs, delivery and installation. In the worked example below, one pivot door goes from enquiry to installed in 122 days, about four months, and most of the time that can be saved is in the buyer’s hands.
How long does each stage take, from enquiry to installed door?
A custom entrance door passes through thirteen stages. At our factory only production has a fixed length: 35–45 days after drawing approval and deposit. The other stages depend on how fast drawings are agreed, how early freight is booked and how ready the site is. The table shows what sets each one and who controls it.
| Stage | What sets the time | Who controls it |
|---|---|---|
| 1. Enquiry and brief | How long it takes you to gather sizes, photos and the door you like; we reply within 12 hours | You |
| 2. First design direction | Ours is free, usually within one working day | Factory |
| 3. Quote | How complete the brief is | Factory |
| 4. Drawing rounds and approval | Your review time plus redrawing, for each round; the stage that varies most | You and the factory |
| 5. Deposit (50%) | Bank transfer time; production starts when it has arrived | You |
| 6. Production | Ours: 35–45 days after drawing approval and deposit | Factory |
| 7. Photos, video and inspection | We send photos and video of every finished door; your sign-off, or your inspector’s visit | You and the factory |
| 8. Balance (50%) | Paid before shipment | You |
| 9. Crating | Blankets, foam and a wooden crate | Factory |
| 10. Trucking to port, export clearance | Your forwarder’s booking (prices are EXW Wuyi) and the port cut-off | Your forwarder |
| 11. Sea freight | The route: see transit times by market | Carrier |
| 12. Customs clearance | The country, the paperwork and any examination | Your broker |
| 13. Delivery and installation | Crate size, unloading and site readiness; your local installers, with our installation drawings and remote guidance | You and your installer |
Which steps does the buyer control, and which the factory?
The factory controls four blocks: the design direction, drawing turnaround, production and crating. The buyer controls the brief, the site measurements, every approval, both payments, the inspector, the forwarder, the import paperwork and the site. Carriers, customs and public holidays control the rest. So most of the time that can be saved sits on the buyer’s side.
The drawing stage is where projects gain or lose weeks: a drawing changed after approval becomes a new revision, and production waits for its approval. See the shop drawing checklist.

How can you shorten each step?
Answer questions before they are asked. Each item below removes a wait: an open question on the drawing, a deposit still in transit, freight booked after the door is finished, or a missing import document. None makes production faster; they stop time being lost either side of it.
- Send a complete brief. Structural opening sizes, quantity, handing seen from outside, finished floor levels, lock, finish and site date, all in the first message. See what to send a door manufacturer.
- Measure the site up front. Check the built opening during the first drawing round, not after approval. See how to measure an entrance door opening.
- Order samples early. If the colour or relief must be seen first, ask for the sample with the first drawing, so it is not the last open item.
- Sign off quickly. One approver, one marked-up set of comments per round, one numbered revision approved in writing.
- Time the deposit. Pay on the day you approve and send the payment reference. Swift says nearly 60% of payments over its gpi service are credited to the beneficiary within 30 minutes and almost all within 24 hours. Check your bank’s cut-off time, and do not pay on the eve of a weekend or a Chinese holiday.
- Book the inspection ahead. Fix the inspector or the live call for the expected finish date, and have the balance ready. See pre-shipment inspection and what to ask on a video factory tour.
- Book freight early. Appoint your forwarder during production, give them the crate’s outside size and gross weight, and book the sailing.
- Have the documents ready. Agree with your broker what they need from the seller, and get it before the balance is paid. For the US, most Importer Security Filing data is due no later than 24 hours before the cargo is laden aboard the vessel at the foreign port (19 CFR 149.2). For Saudi Arabia, see SABER.
- Have the site ready. The opening finished, floor levels fixed, power for the lock in place, installer and lifting booked. See the installer’s checklist.
Which Chinese holidays stop production, and how do you plan around them?
Two holidays matter most. In 2027 the Spring Festival holiday runs from 5 to 13 February and National Day from 1 to 7 October, under the State Council General Office notice of 5 November 2026. Labour Day, 1 to 5 May, is a third. Many factories stop for longer than the official days.
| Holiday, 2027 | Days off | Make-up working days |
|---|---|---|
| Spring Festival | Fri 5 – Sat 13 February, 9 days | Sun 31 January, Sun 14 February |
| Labour Day | Sat 1 – Wed 5 May, 5 days | Sat 8 May |
| National Day | Fri 1 – Thu 7 October, 7 days | Sun 26 September, Sat 9 October |
Around the Spring Festival, workers travel home. Jay Guo of the MIT Global SCALE Network’s Ningbo China Institute for Supply Chain Innovation writes that factories halt for at least 7–10 days, many for 2–3 weeks, and that ports and warehouses slow down too. Carriers cut sailings around National Day: Drewry counted 79 of 721 scheduled sailings cancelled in weeks 38 to 42 of 2026, about 11%.
- Ask the factory for its own closing and reopening dates, and whether the quoted production days run through the holiday.
- Do not plan a drawing approval or an inspection inside a holiday: the people who answer are off too.
- To sail before the Spring Festival, count back as in the transit-time guide. If production runs through the holiday, add at least the nine official days.
- Book freight for late September or October before the National Day sailings fill.
Worked example: one pivot door, from enquiry to installed
This is an example, not a promise. It assumes one pivot door, a complete brief, two drawing rounds, production at the top of our 35–45 days and a 30-day sea leg. The times for the quote, crating, trucking, clearance and installation are assumptions for illustration. Enquiry to installed door takes 122 days.
| Date, 2027 | Day | Step |
|---|---|---|
| Mon 5 July | 0 | Enquiry: structural opening sizes, photos, handing and the door the buyer likes |
| Tue 6 July | 1 | First design direction |
| Fri 9 July | 4 | Quote |
| Tue 13 July | 8 | Drawing, revision A |
| Mon 19 July | 14 | Opening measured on site; one marked-up set of comments sent |
| Wed 21 July | 16 | Revision B |
| Mon 26 July | 21 | Revision B approved in writing; 50% deposit sent |
| Tue 27 July | 22 | Deposit arrives; production starts |
| Fri 10 September | 67 | Production ends, day 45 |
| Mon 13 September | 70 | Photos, video and a live inspection call; signed off |
| Tue 14 September | 71 | Balance paid |
| Wed 15 September | 72 | Mid-Autumn Festival public holiday |
| Thu 16 – Fri 17 September | 73–74 | Crating |
| Mon 20 September | 77 | Forwarder’s truck collects; export clearance |
| Fri 24 September | 81 | Vessel sails, booked in August |
| Sun 24 October | 111 | Arrives at the destination port |
| Mon 1 November | 119 | Cleared and delivered to site |
| Wed 3 – Thu 4 November | 121–122 | Installed by local installers |
Two choices decide this timeline. The drawing took three weeks because the opening was measured during the first round and comments came back as one set. And the door sailed a week before National Day. Finished ten days later, its crating, collection and sailing would have fallen in the holiday week.

Lead-time checklist
- Complete brief sent, with the site date.
- Opening measured before drawing approval.
- Samples ordered with the first drawing.
- One approver; one revision approved in writing.
- Deposit paid on approval day; reference sent.
- Holiday dates checked with the factory and forwarder.
- Inspection booked for the expected finish date.
- Forwarder appointed during production, with crate size and weight.
- Import documents agreed before the balance is paid.
- Site, power, installer and lifting ready for delivery.
How does this work with Dooream?
We reply to enquiries within 12 hours and send a first design direction, free, usually within one working day. Every door is made to the buyer’s drawing, from one door. Production takes 35–45 days after drawing approval and the 50% deposit. We send photos and video of every finished door before shipment, and you or your inspector can check it at our factory; video factory tours run Monday to Saturday, 14:00–18:00 China time. The balance is paid before shipment. Each door is packed in blankets, foam and a wooden crate and sold EXW Wuyi, so your forwarder collects it. Your local installers fit it with our installation drawings and remote guidance. The full order process is in ordering custom doors from China. Send your opening and site date through our contact page.
Sources, checked November 2026: General Office of the State Council, notice on 2027 public holiday arrangements (国办发明电〔2026〕10号, 5 November 2026, in Chinese); MIT Center for Transportation & Logistics, Jay Guo, Chinese New Year and its impact on the global supply chain (28 January 2025); Tradlinx, container cancellations jump to 11% ahead of Golden Week (15 September 2026, reporting Drewry's Cancelled Sailings Tracker of 11 September 2026); Swift, Swift GPI; eCFR, 19 CFR 149.2, Importer Security Filing.
Quick answers
How long does a custom entrance door from China take from enquiry to installation?
Add up the stages. Design and drawing approval take as long as the answers do; production at our factory takes 35–45 days after drawing approval and deposit; then come checks, crating, trucking, sea freight, customs, delivery and installation. In our worked example, one pivot door takes 122 days, about four months, from enquiry to installed.
Which steps can the buyer speed up?
The brief, the site measurements, drawing approval, the deposit, samples, the freight booking and the import documents. Production is the factory's fixed block. Most of the time that can be saved is lost before production starts or after the door is finished.
Which Chinese holidays affect door production in 2027?
Under the State Council General Office notice of 5 November 2026, the Spring Festival holiday runs from 5 to 13 February 2027 and National Day from 1 to 7 October; Labour Day, 1 to 5 May, is a third. Many factories stop for longer than the official days around the Spring Festival, so ask for the factory's own dates.