How long does it take to ship an entrance door from China? Ports, transit times and the full timeline

The door-to-door timeline for a crated entrance door from Zhejiang, sea transit times to the Gulf, Australia, the US and Europe, 2026 route disruptions and Chinese New Year 2027.

By Alan, Dooream factory, Wuyi · 18 November 2026

A dark door frame wrapped in clear film, with metal fixing straps along one side, resting on wooden packing in a workshop
A door frame wrapped in film on wooden packing in our workshop in Wuyi.

Short answer: count four blocks: our 35–45 days of production after drawing approval and deposit, getting the crate onto a ship, the sea leg, and import clearance and delivery. In carrier schedules checked in November 2026, the sea leg from Shanghai or Ningbo is about 14 days to Los Angeles, 14–22 days to Sydney or Melbourne, 28–38 days to the US East Coast and 36–42 days to Northern Europe around the Cape. Gulf routes are disrupted, so confirm the route before you promise a date.

How long does a door take from a Chinese factory to site?

Add up the chain below. Production is the longest fixed block. The sea leg depends on the route and the carrier. The steps either side of it depend on cut-offs, paperwork and how quickly people answer. A missed cut-off or a late approval costs time just as surely as a slow ship.

  1. Drawing approval and deposit. Production starts only when both are in.
  2. Production: 35–45 days at our factory.
  3. Photos, video and balance. You check the finished door and pay the balance.
  4. Crating: blankets, foam and a wooden crate.
  5. Truck to port and export clearance, arranged by your forwarder.
  6. Port cut-off and vessel. The container must reach the terminal before the carrier’s cut-off.
  7. Sea transit, plus any transhipment.
  8. Arrival, import clearance and delivery to site.

Which port does a door from Zhejiang ship from?

Our factory is in Wuyi County, Jinhua, in inland Zhejiang. The nearest large container ports are Ningbo-Zhoushan and, a little further away, Shanghai. Containers from Jinhua also reach Ningbo-Zhoushan by sea-rail train from Yiwu. Compare sailings from both ports: the table shows the same carrier can be days faster from one than the other.

How long is the sea transit to each market?

About 14 days to Los Angeles, 14–27 days to the main Australian ports, 28–38 days to the US East Coast and 36–42 days to Northern Europe around the Cape. These are port-to-port days published by carriers, checked in November 2026, for Shanghai and Ningbo and different services. Schedules change every week, so ask your forwarder for the actual sailing.

Market Port Days at sea from Shanghai or Ningbo Carrier source
Gulf Jebel Ali 16–17, as planned before the 2026 disruption Maersk
Gulf Dammam 18–19, as planned; bookings suspended in November 2026 Maersk
Gulf Jeddah 18–19, as planned Maersk
Australia Sydney 14 (Shanghai, Qilin) to about 18 (Ningbo, Dragon) Maersk
Australia Melbourne 17 (Shanghai, Qilin) to about 22 (Ningbo, Dragon) Maersk
Australia Brisbane About 27 (Ningbo, Dragon, after Sydney and Melbourne) Maersk
US West Coast Los Angeles 14 Hapag-Lloyd
US West Coast Oakland 22–38 Hapag-Lloyd
US East Coast Charleston 28–32 Hapag-Lloyd
US East Coast Savannah 33–37 Hapag-Lloyd
US East Coast New York 33–38 Hapag-Lloyd
UK London Gateway 36–38, via the Cape Hapag-Lloyd
Northern Europe Rotterdam 37–42, via the Cape Hapag-Lloyd
Northern Europe Hamburg 41–42, via the Cape Hapag-Lloyd

The Gulf figures come from Maersk’s undated Asia–Middle East network sheet. The Dragon figures are worked out from Maersk’s August 2026 proforma berth days. The Hapag-Lloyd figures come from its 2026 East-West network brochure, which routes Asia–Europe ships around the Cape of Good Hope; its transit tables are dated 1 September 2025.

Some Asia–Europe ships use Suez again. On 14 September 2026, Maersk said its Gemini AE5 Asia–North Europe service, run with Hapag-Lloyd, would sail via Suez instead of the Cape, from a westbound sailing on 21 September. Further changes, it said, depend on stability in the Red Sea. Xeneta data reported that month put nine Cape services from Yantian to Rotterdam at 41 days on average, and one Suez-routed ship at 27 days. Ask which way your vessel goes.

What is disrupting the routes in November 2026?

Mainly the Gulf, whose ports lie behind the Strait of Hormuz. Maersk’s operational status of 12 November 2026 said:

  • Saudi Arabia: dry bookings to Dammam and Al Jubail suspended; bookings accepted to Jeddah and King Abdullah Port. Saudi cargo, including cargo for Riyadh and Dammam, moves through Jeddah and on by the Jeddah landbridge.
  • UAE: dry bookings accepted only for Khor Fakkan and Jebel Ali. Khor Fakkan had vessel congestion and limited berthing, and selected shipments booked to Khor Fakkan were changed to Jebel Ali.
  • Transhipment: cargo booked to Kuwait, Iraq, Qatar, Bahrain and the UAE transships via Salalah and Khor Fakkan.
  • Large crates: out-of-gauge cargo, which sticks out of its container, accepted only on a limited basis: to Jeddah, Salalah and Khor Fakkan, and to Jebel Ali and Abu Dhabi via Fujairah.
  • Insurance: some insurers had reduced or withdrawn cover for shipments into the Red Sea and the Gulf of Oman.

For the paperwork, see our guides to importing into the UAE and Saudi Arabia and SABER.

Full container or shared container for one or a few doors?

A full container (FCL) is booked for your cargo alone. It can be loaded at the factory and sealed there. A shared container (LCL) usually costs less for one crate but adds time and handling. The crate goes to a container freight station (CFS), is packed with other cargo, and is unpacked again at a CFS at destination.

Flexport puts the CFS cut-off usually about five days before sailing, against about two days for full containers at the container yard. Each extra lift is another chance of a dent. For a large pivot door, or several doors, ask your forwarder to compare both.

Will an oversized pivot door fit in a 40 ft high cube?

Hapag-Lloyd lists its 40 ft standard high cube as 12,032 mm long, 2,350 mm wide and 2,700 mm high inside, with a door opening of 2,340 × 2,597 mm. The crate, not the leaf, must pass that opening. Lying flat, its width must be under 2,340 mm. Standing on edge, its shorter side must be under 2,597 mm.

A crate bigger than that both ways needs another box. Hapag-Lloyd’s 40 ft open-top high cube has a roof opening of 2,192 × 11,552 mm, and anything taller than the box makes it out-of-gauge. Out-of-gauge cargo, on an open top or a flat rack, is booked separately, and in November 2026 it faced the Middle East limits above. We make pivot doors up to 4,000 × 8,000 mm, so ask for the crate’s outside size and gross weight before you approve the drawing. See how big and heavy a pivot door can be.

Packing a door into its crate in our workshop. The crate's outside size decides which container it needs.

Can doors go by air?

Only small parts. A crated entrance door is too large and heavy for air freight to make sense. Air suits a lock part, a handle or a set of seals sent separately. For how crates protect the door at sea, see crating and shipping damage.

How does Chinese New Year 2027 affect a door order?

The State Council notice of 5 November 2026 sets the 2027 Spring Festival holiday at 5 to 13 February, nine days. Sunday 31 January and Sunday 14 February are working days. Ask the factory and your forwarder for their own closing dates.

Carriers thin out sailings around the holiday. For 2026, Maersk blanked 7 eastbound transpacific sailings leaving Asia between 13 and 28 February. It also blanked 5 Asia–Europe sailings in weeks 8 and 9, citing lower demand and a reduced workforce to handle cargo.

Count back from the holiday. For a door to sail before it, 45 days of production must end in late January. That means drawing approval and deposit by about the second week of December 2026.

Who controls each step of the timeline?

Step Typical time Who controls it
Drawing approval and 50% deposit Depends on how fast drawings are agreed You and the factory
Production 35–45 days Factory
Photos, video, 50% balance Before shipment You
Collection, trucking, export clearance Book it during production Your forwarder
Port cut-off About 2 days before sailing (FCL), about 5 (LCL CFS) Carrier and terminal
Sea transit and transhipment 14–42 days, by route Carrier
Import clearance and delivery Depends on country and inspections Your broker and haulier
Installation Local Your installer

Planning checklist

  • Drawing approved and deposit paid early enough for your site date and for Chinese New Year.
  • Crate outside size and gross weight checked against 2,340 × 2,597 mm.
  • Forwarder appointed during production, with EXW collection and loading agreed (Incoterms guide).
  • Port, route and transhipment confirmed in a dated quote: Ningbo or Shanghai, Cape or Suez.
  • FCL or LCL chosen, and the cut-off in your programme.
  • Cargo insurance from factory to site, including war risks on Gulf and Red Sea routes.
  • Inspection booked before the balance is paid (pre-shipment inspection).
  • Import paperwork started early: USA, Australia, UAE, Saudi Arabia.
  • Landed cost worked out (EXW vs landed).
  • Installer and lifting booked for the delivery date.

How does this work with Dooream?

We sell EXW from our factory in Wuyi County, Jinhua, Zhejiang, so your forwarder collects the crate and books the freight. For another Incoterm, ask, and we confirm case by case. Production takes 35–45 days after drawing approval and the 50% deposit. We send photos and video of the finished door before shipment, and the other 50% is paid before it ships. Each door is packed in blankets, foam and a wooden crate. The full order process is in ordering custom doors from China. Send your opening and site date through our contact page.

Sources, checked November 2026: Maersk, Asia to Middle East network one-pager (undated), Qilin service launch (22 May 2026), Dragon service proforma update (4 August 2026), structural changes to AE5, AE11, AE12 and ME2 (14 September 2026), operational status (Middle East Operational Update 54, 12 November 2026), Chinese New Year 2026 transpacific schedule adjustments and Chinese New Year changes to Far East Asia–Europe services (23 December 2025); Hapag-Lloyd, East-West service network 2026, Cape of Good Hope, 40' standard high cube and 40' open top high cube; Tradlinx, four more Gemini services back through Suez (16 September 2026, reporting Xeneta data); Flexport, container freight station cut-off; China Daily, Yiwu sea-rail service via Ningbo-Zhoushan Port (13 August 2025); State Council General Office, notice on 2027 public holidays (5 November 2026, in Chinese).

Quick answers

How long does sea freight from China take for an entrance door?

In carrier schedules checked in November 2026, the sea leg from Shanghai or Ningbo is about 14 days to Los Angeles, 14–22 days to Sydney or Melbourne, 28–38 days to Charleston, Savannah or New York, and 36–42 days to London Gateway, Rotterdam or Hamburg around the Cape. Add production, the port cut-off, customs and delivery.

Will a large pivot door fit in a 40 ft high cube container?

Only if its crate passes the doors. Hapag-Lloyd gives the door opening of its 40 ft high cube as 2,340 mm wide and 2,597 mm high. A crate bigger than that both ways needs an open-top container or a flat rack, and in November 2026 Maersk accepted out-of-gauge cargo to the Middle East only on a limited basis.

When is Chinese New Year 2027, and how does it affect shipping?

The official holiday is 5 to 13 February 2027, under the State Council notice of 5 November 2026. Carriers cancel sailings around it. For the 2026 holiday, Maersk blanked 7 eastbound transpacific sailings leaving Asia between 13 and 28 February and 5 Asia–Europe sailings in weeks 8 and 9.

Ask the factory