Short answer: place the custom entrance door order as soon as the structural opening, lintel, finished floor datum and wall cladding build-up are fixed—usually four to five months ahead of site handover when importing from China. Do not wait until interior tiling is finished to start drawing approvals, and do not hang a finished architectural leaf while wet plastering, screed pouring and heavy site deliveries are still under way.
Why does timing an imported custom door matter so much on a new build?
A custom entrance door sits on the critical path between structural shell completion and weather-tight lock-up. Ordering too early forces guesswork on unbuilt walls; ordering too late leaves an open porch delaying alarm testing, air-conditioning commissioning and final handover.
For a complete breakdown of the 13 factory and freight steps—including our 35–45 days of production after drawing approval and deposit plus sea transit—see our custom entrance door lead time guide. On site, the goal is matching those off-site weeks against the building’s construction sequence so the crate arrives just as the opening is ready for clean second-fix installation.
| Site construction phase | Site status | Door project action | Risk if done out of order |
|---|---|---|---|
| 1. Concept and foundation design | Floor plans and elevations drafted | Confirm opening type, clear passage, pivot structural load and approximate crate path | Undersized lintel or underfloor heating pipes laid under the pivot point |
| 2. Structural frame / blockwork complete | Concrete lintel, masonry piers and rough opening built; wet trades pending | Measure structural opening; lock FFL datum, cladding thickness and conduits; approve drawings and pay deposit | Guesswork sizes fail to match actual as-built masonry |
| 3. Rough-in and first fix (door in production) | Temporary site door in place; plaster, screed, stone, wiring underway | Run smart-lock/intercom conduit; finish stone floor at threshold; order crane/installer | Wet mortar or dust damages finished door if hung prematurely |
| 4. Crate arrives at port and site | Cladding and threshold floor cured; heavy dirty trades finished | Uncrate, inspect leaf and frame, fit frame plumb, hang leaf, test lock and drop seal | Delay in customs or missing lifting gear holds up lock-up |
| 5. Handover and commissioning | Reveals caulked; final cleaning complete | Peel protective film within manufacturer time limit; test all keys and hand over O&M pack | Film baked onto hot paint or builder codes left active |
What must be fixed on site before you approve the shop drawings?
Never approve production drawings based solely on early architectural tender drawings if blockwork or steel framing is already going up. Even a 20 mm concrete tolerance or a switch from 20 mm porcelain to 30 mm limestone cladding changes frame projection and fixing gaps.
Lock these six site facts in writing before issuing final drawing sign-off:
- As-built structural width, height and diagonals. Measure the actual masonry or steel opening at three widths and three heights as set out in how to measure an entrance door opening.
- One finished floor level (FFL) datum. Mark the exact finished floor height inside and outside relative to a fixed structural datum so sill height, bottom clearance and automatic drop seals match the real tile or stone top surface.
- Wall finish and reveal thickness. Confirm plaster, render, timber panelling or dry-hung stone thicknesses on both inside and outside faces so the outer frame edge sits flush or recessed exactly as detailed.
- Top-pivot and lintel bearing. On an offset pivot door, confirm concrete or structural steel above the head is continuous and stiff enough for the pivot loads calculated by the engineer.
- Underfloor heating exclusion zone. Keep hydronic pipes and electric heating mats clear of the floor plate and any anchor screws (pivot door underfloor heating).
- Electrical conduit and relay location. Confirm where low-voltage power or PoE intercom cables exit the wall or lintel so no cables cross open masonry after stone cladding is glued on.

Should you order off architectural plans or wait for the built opening?
You can start design direction, sample requests and preliminary quotes from architectural plans, then verify the built rough opening before finalising manufacturing widths and heights. That split saves four to six weeks without risking a door that does not fit the masonry.
- Start early while the shell rises. During foundation or superstructure work, send the elevation, rough dimensions and design preference to get a first design direction, order a 20 × 20 cm colour and relief sample, and confirm hardware, smart-lock power and freight route.
- Freeze production only on verified masonry or a controlled sub-frame. Once concrete piers or steel goalposts are cast, measure the real opening and confirm packing gaps (typically 10–15 mm per side for shimming and perimeter sealing). If a contractor must order before walls are plastered, build a rigid steel sub-frame on site to exact drawing dimensions so masonry follows the sub-frame rather than the reverse.
How do you protect the entrance between lock-up and final door hanging?
Fit an inexpensive temporary site door during plastering, floor grinding and interior cabinetry, and keep the custom architectural door stored flat in its unopened or inspected crate until heavy site dust ends. Builders pushing wheelbarrows, plaster mixers and marble slabs through a finished entrance will chip edges and grind grit into concealed floor plates and multipoint lock bolts.
- Before delivery: ensure the villa roof, windows and secondary doors are closed so the site is dry.
- If the frame must be built into wet stone: check whether a two-stage sub-frame can go in early while the finished leaf and hardware stay safely crated until the last week before handover.
- Film removal: protective plastic film protects painted aluminium during light finishing, yet adhesive left under strong summer sun bakes onto coatings. Follow the installer’s limit (for example, Stegbar specifies removing protective film within 90 days of delivery) and peel film promptly once dirty trades leave.
What common scheduling mistakes delay villa handover?
Most delays come from misaligned site decisions rather than factory machinery. Watch for five recurring bottlenecks:
- Forgetting Chinese public holidays. Spring Festival (5–13 February 2027 officially, with longer workshop and port slowdowns) and National Day (1–7 October 2027) shift both production completion and vessel sailings.
- Approving samples last. Waiting until shop drawings are signed before requesting a colour or carved relief sample outdoors adds two to three weeks of courier and sign-off time.
- Late stone or screed changes. Adding heated screed or thicker marble slabs after production starts changes the leaf undercut and threshold height.
- Skipping customs and anti-dumping checks. Confirm HS code, duty and any destination test or import certificate requirements before deposit payment rather than when the ship docks.
- No lifting crew booked. A large armoured door cannot be carried into a villa by two finish carpenters; book vacuum lifters or a site hoist ahead of container arrival.
New-build ordering timeline checklist
- Month −6 to −5 (structural design): confirm door type, rough opening, head beam, underfloor heating exclusion and power conduit on tender drawings.
- Month −5 (shell rising): send design brief and request 20 × 20 cm face finish samples for outdoor approval beside real stone or render.
- Month −4 (opening built): laser-measure real structural opening, lock FFL datum and wall build-up, approve final shop drawings and pay 50% deposit.
- Month −3 (production): run wall conduits, appoint freight forwarder, confirm crate dimensions and check import paperwork.
- Month −2 (factory inspection & sailing): inspect finished photos/video, pay 50% balance, ship crate while temporary door protects site wet trades.
- Month −1 to handover: finish stone threshold and wall cladding, hang finished frame and leaf cleanly, test smart lock and peel protective film.
How does this work with Dooream?
Dooream (Zhejiang Jingyi Door Industry Co., Ltd., Wuyi County, Jinhua, Zhejiang, China) builds complete custom aluminium armoured entrance doors from one door—single, double and unequal double doors up to 3,000 × 6,000 mm, and offset pivot doors up to 4,000 × 8,000 mm on pivot hinges, most often FritsJurgens. Send your architectural plans early: our first design direction is free and usually ready within one working day, and we can dispatch 20 × 20 cm face samples while your structure is still going up. Once your built opening and FFL are confirmed on the shop drawing and the 50% deposit arrives, production takes 35–45 days, with the 50% balance due before shipment EXW Wuyi. Our thermal-break construction, with PA66 polyamide insulating strips in the aluminium profiles, can be used with any of our designs; we don’t publish a U-value for it, and if your project needs one, we can arrange a test for your order, usually at the buyer’s cost. Your local builder or installer fits the door using our installation drawings and remote guidance, backed by a two-year warranty from shipment. Send your project programme and drawings via our architects page or contact page.
Sources, checked November 2026: General Office of the State Council, notice on 2027 public holiday arrangements (5 November 2026, in Chinese); FritsJurgens, floor plates; Stegbar, care and maintenance (protective film guidance).
Quick answers
At which construction stage should you order a custom villa front door?
Order after the structural masonry or concrete entrance frame and lintel are built and verified, and the architectural finished floor level (FFL) datum, wall cladding thickness and electrical conduits are locked—typically four to five months before you want the door fitted and sealed.
Should you install a custom finished front door before plastering, tiling and painting?
No. Fitting a finished architectural door during heavy wet trades risks cement splashes on fluorocarbon paint, dust in pivot bearings and knocks from scaffold boards. Fit a temporary site door during rough work, finish the wet trades around the frame opening, then hang the custom door late in second fix.
Can you change the floor level or stone cladding thickness after approving door shop drawings?
Not safely. Because custom doors are built to exact opening widths, head heights and finished floor clearances, changing screed depth or stone thickness later can trap the bottom drop seal or expose unsightly gaps around the frame.